Kärtnen Netz Logo - Link zur kaerntennetz.at Startseite

GreenSwitch

Cross-border PCI Project

The Project

For this cross-border project of common interest (PCI), we have partnered up with several companies from Slovenia and Croatia. The aim of the project is to optimise the use of the existing electricity infrastructure. Moreover, it will allow new technologies and advanced functionalities to be integrated into the transmission and distribution grids. This will enable a greater integration of renewable energy sources into the grid infrastructure and thus increase the security of supply.

 

 

Goals

Introduction of smart equipment 
Security of supply
Greater integration of renewable energy sources

Duration

2023 to 2028 

Investments

146 Mio. €
EU Funding: 73 Mio. €
Thereof: 46 Mio. € KNG
EU Funding: 23 Mio. €

 

Partners

Croatia (HOPS, HEP) 
Slovenia (ELES, Elektro Celje, Elektro Gorenjska, Elektro Ljubljana)

Timeline

2021

Application 5th PCI list

2023

CEF co-funding granted

2023-2025

Permit granting

2024-2028

Construction & Commissioning

Expected Impacts

 

 

 

Increased controllability of the power grid through automation

Expansion of capacity for the existing network

 

Expansion of cross-border network capacity

Increased controllability of transformer stations through automation

 

Lower peak demand with the use of flexibility sources

 

 



 

Our GreenSwitch Projects in Carinthia

 

The sub-projects

  • Automation of two new primary substations (110/20kV)
  • Automation of around 60 secondary substations (20/0,4kV) 
  • Expansion of the medium voltage grid (150km of underground cables) 
  • Laying of fiber optic cables (70km)
  • Upgrade of Advanced Distribution Management System (ADMS) functionalities
  • Upgrade of existing and construction of new cross-border emergency power connections (20kV from Austria to Slovenia)

Our primary substation Winklern

The new primary substation Winklern is necessary in order to supply our customers, private households as well as companies, in the Mölltal with sufficient and reliable electricity over the coming decades. This includes the municipalities of Stall, Rangersdorf, Winklern and Mörtschacher.

It will be constructed near the municipality of Lamnitz, directly under the existing 110kV overhead line that runs from the primary substation Außerfragant via the mountain range Kreuzeck Group to the municipality of Oberdrauburg.
The primary substation Winklern will consist of the following plant components: a 110-kV switchgear five 110-kV overhead line connections, a 110/20-kV secondary substation, a 20-kV arc suppression coil  and seven 20-kV cable connections. 

The new substation will make the grid infrastructure in the upper Möll Valley fit for the future.


In a nutshell:
•    Construction of a new primary substation
•    Duration of 2 years

Automation of secondary substations

This sub-project involves not only automating existing transformer stations but also the construction of new "smart" stations. The automated transformer stations will be connected to our grid control system with remote-controlled and remote signalling switching devices, as well as short-circuit indicators with remote metering function. Upgrading the transformer stations is one of the key factors in the successful operation of the grid control system and therefore enables increased security of supply.


In a nutshell:

New construction and automation of 60 transformer stations 
Duration 2023 to 2028

News

Consortium Meeting

Klagenfurt, 13. November 2023

Regular consortium meetings are held at the various locations as part of the project. On 13 and 14 November, colleagues from the Slovenian and Croatian grid operators visited Kärnten Netz. After a brief introduction by the management, the participants were able to gain an insight into our operational activities during a visit to the grid control centre. During the two days, the progress of the individual sub-projects of all project partners was presented and further steps were defined together.

4th PCI Energy Days

Brussels, 28-29. November 2023

The team presented the project at the PCI Energy Days in Brussels and welcomed the Director for Green Transition and Energy System Integration, Catharina Sikow-Magny, to the project stand.

 

 

 

 

Cross-border exchange of experience between distribution system operators

between Kaernten Netz and Elektro Ljubljana

An exchange of experience recently took place in Ljubljana with the neighbouring distribution system operators Kaernten Netz (KNG) and Elektro Ljubljana. In future, the partnerships established in the CEF-funding project "GreenSwitch" will be strengthened not only for project implementation, but also for exchanging experiences. Renewable energies, asset management, energy communities and the digital twin were some of the topics on the agenda of the recent cross-border. Various experiences and examples of best practice were exchanged between the employees in intensive discussions in Ljubljana. Both partners can only confirm the statement: "The language barrier shouldn't stop us from learning from each other”.

DISCLAIMER

Co-funded by the European Union. Views and opinions expressed are however those of the author(s) only and do not necessarily reflect those of the European Union or the European Climate, Infrastructure and Environment Executive Agency (CINEA). Neither the European Union nor the CINEa can be held responsible for them.